Ankapark Facts

$801 MILLION — 38 BILLION TL

Remained open for 11 months; leaving behind a massive cost and a public file that demands accountability.

Open the File →

Location & Risk

HIGH FLOOD RISK ZONE

ANKAPARK… was located in an area where three streams merge and flood risk is high. Existing trees in Atatürk Forest Farm were also cut down for ANKAPARK.

View Risk Analysis →

Pricing Concerns

2,573 ITEMS: $4.19 MILLION DIFFERENCE

The records show discrepancies between the amounts paid and manufacturers' quotations—differences cited in allegations of losses to the public purse.

Examine Comparison →

Idle Units

NOT INSTALLED • DISMANTLED • NEVER OPERATED

The records list attractions that were never installed, were later dismantled, or never entered service. The Monorail is one of the clearest examples.

View Idle Units →
⚠️ Warning: Contains Real Figures 📄 Official Documents 🗂️ 2018–2022 File

Ankara's 38 Billion TL Reckoning

801
Million Dollars
Total Cost
11
Months
Remained Open
38
Billion TL
Current Value

The "dream park" built for $801 million remained open for only 11 months. It opened 10 days before the election, and the operator closed it 8 months later. The resulting loss to the public is 38 billion TL at current exchange rates. Here is the story of waste, negligence, and mismanagement.

🔥 TOTAL WASTE

This is Not Just a Number, It's Ankara's Lost Future

0 TL

38 billion TL is the total resource cut from Ankara's priorities, from education to transport, social support to infrastructure. This counter makes the cost of lost opportunity visible second by second.

Every Day It Remained Open:

113
Million ₺
That is how much of Ankara residents' money was wasted
38 billion ₺ ÷ 336 days = 113.1 million ₺/day
($801 million × 47.44 TL/$ ≈ 38 billion ₺)

2022 Capital Survey

ANKARA RESIDENTS WANTED A RECREATION AREA

In 2022, Ankara Metropolitan Municipality asked residents, “What do you think ANKAPARK should become?”

Approximately 80,000 people took part in the survey, and 95 percent wanted the site to be converted into a recreation area.

In response, Ankara Metropolitan Municipality launched a comprehensive transformation process to return ANKAPARK to the people of the capital and converted it into a recreation area.

Location & Planning Error

They Built a Park in a Flood Zone

Ankapark was built along the Ankara Stream, very close to the flood corridor affected by the Söğütözü and Dikmen streams. Reports by the Ministry of Agriculture and Forestry clearly mark sections of this corridor as high risk and very high risk.

Ankara Stream Söğütözü Stream Dikmen Stream
Map showing the relationship between the Ankapark area and the Ankara Stream flood corridor
The area where the Ankara Stream flood zone overlaps with the Ankapark layout.
Map showing high and very high risk zones according to the Ministry of Agriculture and Forestry report
High risk and very high risk zones mentioned in the report.
Examine detailed analysis on the Report & Facts page →

Figures That Reveal the Scale of the Damage

111 Million ₺
Determined Damage
Documented by expert report
53 Units
Idle Attractions
Never installed or dismantled
27 Million ₺
Annual Electricity
Required even for a closed park
15+ Files
Foreclosure Attempts
Attempts made to seize public property

⚡ Key Highlights

🚝 Monorail

$1.98 Million

Never installed, never operated. No driver seat, no digital panel, seats made of cheap plastic. Now rotting away.

Details →

🦖 Dinosaurs

3X HIGHER

$2.78M paid for 246 dinosaurs. 2021 price quote: $1M. Did the difference go into someone's pocket?

Details →

🤖 Transformers

$965,000

30+ Transformers robots were bought with the Social Services budget. Children's social welfare budget went to war toys.

Details →
38 Billion ₺
Total waste taken from the pockets of Ankara residents
(Calculated at $801 million × 47.44 TL/$ exchange rate)
💡 Real Cost: The total cost of Ankapark is $801 million. Calculated at today's dollar exchange rate (47.44 TL/$), it is worth approximately 38 billion TL.